当前位置: X题卡 > 所有题目 > 题目详情

Cost performance measurement is BEST done through which of the following ?()

查看本题答案

你可能感兴趣的试题

CVs are severe, and a realistic measure of performance is needed  revised cost estimates are prepared and distributed to stakeholders  corrective action must be taken to bring expected future performance in line with the project plan  EAC shows that additional funds are needed to complete the project even if a scope change is not needed  
the project is ahead of its planned schedule  less work was completed than was planned  the cost overrun for work completed  the cost under-run of performance to date  
issuing budget updates  revising the cost baseline  corrective action e. g. adjusting schedule activity budgets  closing the project  
Performance measurement.  Scope change control system.  Inspection.  Earned value.  
issuing budget updates  revising the cost baseline  corrective action adjusting schedule activity budgets  closing the project  
the project is ahead of its planned schedule  less work was completed than was planned  the cost overrun for work completed  the cost under-run of performance to date  
Asking for a percent complete from each team member and reporting that in the monthly progress repor  Calculating earned value and using the indexes and other calculations to report past performance and forecast future performanc  Using the 50/50 rule and making sure the life cycle cost is less than the project cos  Focusing on the amount expended last month and what will be expended the following mont  
strategic planning  alternative objectives inventory  management by objectives  contingency planning  
the good sealing performance and the simple structure  the good sealing performance and the short life expectancy  the good sealing performance but the short life expectancy  the good sealing performance and the lower cost  
The earned value(EV)and the actual cost to date(A .  The cost performance index(CPI)and the cost variance(CV).  The actual cost to date(A and the cost performance index(CPI).  The actual cost to date(A and the estimate to complete(ET .  
project charter  baseline  performance measurement  milestones  
to the current date of the EV and the actual cost of AC  cost performance index CPI and cost variable CV  to the current date of the actual cost of AC and the cost performance index CPI  the actual cost of AC and ETC to the current date  
Cost overrun of the estimate  Cost according to the estimate  Cost underrun of the estimate  Early progres  
Consider overtime work as part of the job.  Prepare a cost baseline.  Use earned value management to monitor performance.  Estimate and budget controllable and uncontrollable costs separately.  
divide it by the schedule performance index  multiply it by the schedule performance index  multiply it by the cost performance index  divide it by the cost performance index  
the cost savings for work completed  the project is ahead of its planned schedule  the cost overrun for work completed  less work was completed than was planned  
project management plan  performance measurement baseline  earned value calculations  none of the above  
product analysis  risk measurement  alternatives identification  benefit/cost analysis  
work breakdown structure  project schedule  cost baseline  cost budget  
the cost savings for work completed  the project is ahead of its planned schedule  the cost overrun for work completed  less work was completed than was planned  

热门试题

更多