1最佳选择题 3分

Yourpreferredresourceisnotavailableatthetimeneeded

  • A. Negotiate with management to get the resource. The management is responsible for provision of resources for the project.
  • B. Assess your alternatives.
  • C. Begin the task early.
  • D. Use reserves to increase resources assigned to those tasks.
查看答案

正确答案: -

本题解析: 暂无解析

2最佳选择题 3分

Youareassignedtobetheprojectmanagerinthemiddleofth

  • A. Discuss it with the project team.
  • B. Recalculate baselines.
  • C. Renegotiate the contract.
  • D. Meet with the customer.
查看答案

正确答案: -

本题解析: 暂无解析

3最佳选择题 3分

Whenisintegrationperformed

  • A. Project planning.
  • B. Project execution.
  • C. At key interface points.
  • D. At the end of each project management phase.
查看答案

正确答案: -

本题解析: 暂无解析

4最佳选择题 3分

Whenshouldtheprojectbaselinebechanged

  • A. It should not he changed.
  • B. Only for changes that have been approved by the change control board.
  • C. At each project team meeting.
  • D. For all implemented changes.
查看答案

正确答案: -

本题解析: 暂无解析

5最佳选择题 3分

Aprojectmanagerhasmadeachangetotheproject.Whatshou

  • A. Assign resource.
  • B. Revise the project plan.
  • C. Evaluate impact.
  • D. Request change control board involvement.
查看答案

正确答案: -

本题解析: 暂无解析

其他考生还关注了

更多
  • 填空

    试卷分类:PMP项目管理师考试

    练习次数:2次

  • 问答

    试卷分类:PMP项目管理师考试

    练习次数:2次

  • 填空

    试卷分类:PMP项目管理师考试

    练习次数:1次

  • 问答

    试卷分类:PMP项目管理师考试

    练习次数:0次

  • 填空

    试卷分类:PMP项目管理师考试

    练习次数:0次

  • 填空

    试卷分类:PMP项目管理师考试

    练习次数:2次

  • 填空

    试卷分类:PMP项目管理师考试

    练习次数:2次

  • 填空

    试卷分类:PMP项目管理师考试

    练习次数:0次