当前位置: X题卡 > 所有题目 > 题目详情

What are the estimates of the world’s oil and gas reserves?

查看本题答案

你可能感兴趣的试题

analyze  track  level  extend  
$250,000.  $220,000.  $280,000.  $300,000.  
measures  estimates  cancels  represents  
declines  assesses  estimates  maintains  
analyze  track  level  extend  
 Identification of risks.  Work package estimates.   Detailed resource estimates.  The business need for the project.  
scope statement  activity list  project charter  project schedule  
scope statement  activity list  project charter  project  
budget  plan  risk  contract  
$250,000  $220,000  $280,000  $300,000  
Conceptual estimates.  Order of magnitude estimates.  Preliminary estimates.  Bottom-up estimate.  
PERT is superior to CPM  PERT estimates are better than Monte Carlo simulation  CPM uses 3 estimates on a task(pessimistic, optimistic and most likely)  Monte Carlo simulation uses PERT formula  
Identification of risks  Work package estimates  Detailed resource estimates  The business need for the project  
budget  plan  risk  contract  
scope statement  Activity list  project charter  Project schedule  
analyze  track  level  extend  
scope statement  activity list  project charter  project schedule  
PERT is superior to CP  PERT estimates are better than Monte Carlo simulatio  CPM uses 3 estimates on a task(pessimistic,optimistic and most like  Monte Carlo simulation uses PERT formul  
analyze  track  level  extend  
analyze  track  level  extend  

热门试题

更多