当前位置: X题卡 > 所有题目 > 题目详情

In the early days of the internet, the idea that it represented an entirely new and separate real...

查看本题答案

你可能感兴趣的试题

the project float is 5 days  the project may get delayed  the task is not on the critical path  the task is on the critical path  
in the early days most American writers were from Great Britain  people with rich life experiences became writers  there were many writers in the early days of American history  early-day experience provided the foundation for American literature  
Pushes the finish date out ten days.  Delays the early start date of the next dependent task five days.  Allows the project to finish five days earlier.  The finish date doesn't change.  
to getting    to get    for getting    of getting  
The next dependent task's start date will be delayed 15 days.  The duration of the task will be shortened 15 days.  The completion date of the project will be pushed out 5 days.  Both A and C.  
So do I    So I do    So I am    Thanks a lot  
almost  nearly  hardly  likely  
looked back to    looked on    looked back on    look around  
hoped    expected    wished    ordered  
intended    insured    inspected    Inspired  
 the project float is 5 days   the project may get delayed  the task is not on the critical path   the task is on the critical path  
the project float is 5 days  the project may get delayed  the task is not on the critical path  the task is on the critical path  
So do I  So I do  So I am  Thanks a lot  
so few  such few   so little  such little  

热门试题

更多