当前位置: X题卡 > 所有题目 > 题目详情

Project work packages are typically decomposed into smaller components called activities to provide ...

查看本题答案

你可能感兴趣的试题

estimating  reviewing  auditing  expecting  
reviewing  estimating  auditing  expecting  
Integration  Scope  Configuration  Requirement  
Using diagramming techniques like GERT and systems dynamic  Calculating theoretical early and late start and finish dates for all project activitie  Using standardized networks to expedite preparation of project network diagram  Subdividing project work packages into smaller more manageable components for better management contro  
The project manager did not get buy-in from the manager for the resources on the project.  The project manager did not create an adequate reward system for team members to improve their cooperation.  The project manager should have had a meeting with the team member's boss the first time the team member caused trouble.  The project manager does not have work packages.  
Integration  Scope  Configuration  Requirement  
It is the collection of all subsidiary project document  The project charter is the necessary basis for all work packages to be performe  It formally authorizes the projec  It tracks the progress of the projec  
the practice of keeping up with the latest fashions in project management (newest software packages, terms, concepts, etc)  recording and evaluating the trends regarding schedule accomplishment, resource expenditures, and forecasting the impacts of the trends on the future work and ultimate completion of the project  generally impractical and not very useful on larger projects  when the project manager determines the degree to which the schedule is meeting expectations  
The project manager did not get buy-in from the manager for the resources on the projec  The project manager did not create an adequate reward system for team members to improve their cooperatio  The project manager should have had a meeting with the team member’s boss the first time the team member caused troubl  The project manager does not have work package  
It is the collection of all subsidiary project documents.  The project charter is the necessary basis for all work packages to be performed.  It formally authorizes the project.  It tracks the progress of the project.  
developing an approximation of the costs of the resources needed to complete each schedule activity  aggregating the estimated costs of individual schedule activities or work packages to establish a total cost baseline for project performance  searching the cause of positive and negative variances as part of integrated change control process  assuring that potential cost overruns do not exceed the authorized funding periodically and in total for the project  
It is a deliverable or project work component at the lowest level of each branch of the work breakdown structure  It is a summary task at the top level of the WBS  It includes the schedule activities required for completion of the deliverable or project work component  It includes the schedule milestones required for completion of the deliverable or project work component  
reviewing  estimating  auditing  expecting  
the cost savings for work completed  the project is ahead of its planned schedule  the cost overrun for work completed  less work was completed than was planned  
adding activities to the project  expanding the scope of the project  developing a responsibility matrix for work assignments  delineating project work effort into discrete and logical sub-elements  
tracking project performance against cost and schedule  creating a network diagram, with task dependencies  creating a project schedule  assigning resources to work on different work elements  
It is a deliverable or project work component at the lowest level of each branch of the work breakdown structur  It is a summary task at the top level of the WB  It includes the schedule activities required for completion of the deliverable or project work componen  It includes the schedule milestones required for completion of the deliverable or project work componen  
reviewing  estimating  auditing  expecting  
Integration  Scope  Configuration  Requirement  
Project statement of work.  Configuration management requirement.  Project scope statement.  Work breakdown structure.  

热门试题

更多